With the concerted efforts of employees from various departments, the follow-up of the senior management of the Waha Oil Company , and the directives of the National Oil Corporation (NOC ) on the need to work on raising the production capacity of the Alfaragh field, after the formation of a working team from some departments to increase the production capacity in line with the operational conditions of the lab and wells .
The team began conducting pilot tests on August 15,2022 and working to gradually increase production until to reaches an average of (149) MMSCF feet of gas and (9000) barrels of condensates per day .
In this regard the Chairman and members of the Board of Directors of the NOC extend their deepest thanks and appreciation for the efforts of all the workers who contributed to the completion of this outstanding work in which they embodies the spirit of one team and continued through day and night to complete the tests successfully .