Industrial Complex Ras Lanuf Back To Work After Years Of Not Operating.

0
915

On Friday, May 12, 2023, the process of introducing “Naphtha” into the furnaces and operating the cracked gas compressor system (R10-1) commenced, leading to the production phase and following up on the operations according to the approved operation manuals.

This process comes after the success of all operation tests for the work systems of the various units in the ethylene factory, which started several months ago, confirming the readiness of the production units in the industrial complex to keep up with the requirements of operating the plant.
Through this step, the Ras Lanuf Oil and Gas Processing Company has reached an advanced stage in the plan to restart the industrial complex, which started in 2019.
On this occasion, the chairman and members of the board of directors of the National Oil Corporation expressed their praise regarding the efforts made and the distinguished work carried out by the Ras Lanuf Oil and Gas Processing Company.

The chairman of the board also emphasized that all stages of the operation process must be carried out in accordance with safety procedures and requirements to ensure the wellbeing of all individuals and safety of equipment, on the way leading to the final production phase.

SOURCENOC