Completion of maintenance work for the main crude transmission line at Waha Oil Company.

0
1293
On Wednesday, January 05, 2022, the technical teams at Waha Oil Company completed the maintenance operations of the main 32-inch oil transmission line connecting the fields (Al-Samah – Al-Dhahra) to ESidra port at the points 70 km and 71 km, which continued over 24 hours for two consecutive days.
The work was completed ahead of schedule and the task was accomplished within two days instead of a week and by national hands, which contributed to reducing the losses resulting from the halt in production, which was estimated to reach about one million barrels, and the production of the Waha Company was raised by 200 thousand barrels per day.