On 7 August 2021, the Council of Ministers of the Government of National Unity in Libya approved the award of a number of important contracts to be concluded by way of direct contracting with international companies. The decisions, issued through Council of Minister Decrees, explicitly exempt the projects from the rules of the Administrative Contract Regulation that governs public tenders and contracting with public sector entities.

 

Company Project Volume CoM Decree (of the year 2021)
Orascom Construction Implementing the Mellitah Gas Fired Power Plant Project and connection to the national electricity grid.

Contracting with the JV ACICO Group & Shaker Group for consulting services.

EUR 982,998,148.00

 

 

EUR 12,570,000.00

204
Al Rowad Engineering for Contract & Supply

شركة الرواد الهندسية للأنشاءات

Implementing         the Derna    Power   Plant Project and connectio to the national electricity grid

Long-term maintenance and the supply of spare parts at an equal value

Contracting with the JV ACICO Group & Shaker Group     for consulting services.

 

EUR 868,301,106.00

 

 

EUR 135,000,000.00

 

 

EUR 12,570,000.00

 

 

 

205
Imprägnierwerk Marmetschke GmbH Supplying         13,694 wooden poles with a length of 11 meters EUR 2,151,053.00 207

1 The information in this list is based on the CoM Decrees as published by the Government of Libya. We do not assume any responsibility for the completeness or accurateness of this project list.

 

(for a construction in western Tripoli)
Finntrepo Ltd Supplying 44,390 wooden poles with a length of 9 meters (for a construction in western Tripoli) EUR 5,472,399.00 208
Standardkessel Baumgarte GmbH Carrying out a major overhaul of the steam units/steam generators     at     the Zawwia Power Plant EUR 89,258,081.00 209
Alkhansaa Building Maintenance

شركة الخنساء للخدمات

Supplying clothes and (professional) equipment     for    the health care and safety sector EUR 3,892,050.00 210
VA Tech Wabag Carrying out a major overhaul of the desalination plant in northern Benghazi EUR 6,130,600.00 211
G&D Italia Suppling                and installing a power generator EUR 7,388,671 212
Iskraemeco (by Elsewedy Electric) Supplying 320,000 electric meters (single phase) and 106,000 electric meters (three phase) EUR 15,514,900.00 214
WIGI SWISS Supplying              and installing rotary disk filters EUR 2,225,066 216
Company Qalb شركة قلب المتوسط Importing of oil and lubricants GBP 599,262.5 217
Johnson Supplying              and

installing                  air conditioning systems to and at the Zawwia power plant

USD 1,105,000 218
WIGI SWISS Supplying    oils    and grease to all stations GBP 786,750 219

 

NMOS Ltd Supplying oil and lubricants to all power plants and stations GBP 656,742.00 220
Oil Group Libyan LIGOS المجموعة الليبية ( Co. Service )للخدمات النفطية Supplying              and installing a bypass valve to and at the Tripoli West Power Plant EUR 4,700,326 221
WIGI SWISS Supplying a chlorine system to the Tripoli West Power Supplier Station EUR 77,375 222 (no longer in place, replaced by no 229)
Kontrolmatik Supplying a distributed        control system    (DCS)    and performing emergency maintenance           on converter stations in the western region USD 1,075,000 223
WIGI SWISS Supplying a chlorine system to the Tripoli West Power Plant EUR 722,375 229 (replaces decree no. 222)

 

Previous articleMinistry of Industry discusses creation of technology and industry hub with Renewable Energy Centre.